Urban Transformation (Law No. 6306): Current Process

25 Şubat 2026 Real Estate Law 2 dk okuma 17 görüntülenme Son güncelleme: 8 Mayıs 2026

Law No. 6306 on the Transformation of Areas at Risk of Disaster regulates the process of demolition and reconstruction of structures at risk of earthquake and disaster.

Risky Building Detection

  • The Ministry of Environment, Urbanization and Climate Change is authorized.
  • Technical review by licensed organizations.
  • Annotation on title deed with risk report.
  • Malik is informed; Objection period is 15 days.

Destruction Process

  • Demolition within 60 days at the latest after detection of a risky structure.
  • The evacuation period does not exceed 90 days (usually 60 days).
  • Owner approval not required — public interest.
  • Rent assistance (temporary housing) is provided.

Agreement with Contractor

  • Contractor election by 2/3 majority of the owners
  • The remaining 1/3 must participate — the right to object is limited.
  • The flat fee agreement is approved by a notary.
  • Construction inspection company control.

Rent Assistance

  • Temporary shelter assistance to the owner after demolition.
  • Monthly amount depends on region and family size.
  • Paid during construction (usually 18 months).
  • Direct transfer by the Ministry.

Entitlement Calculation

  • Foundation of the square meters of the independent section in the old building.
  • Equivalent or increased square footage in new building.
  • Owner cash/small flat difference according to the terms of the agreement.
  • Discussions on the transfer of "superstructure rights".

Supreme Court HGK and 14th HD - Established Approach

HGK and the 14th HD adopt the strict implementation of the 2/3 majority requirement of the owners in urban transformation, the right of objection of the remaining 1/3 owners is limited, but reasonable payment agreements must be presented so that they do not suffer financial losses in the selection of the contractor.

Typical Disputes

  • Objection to the risk report.
  • Failure to pay rental assistance.
  • Contractor delay/bankruptcy.
  • Entitlement rate debate.
  • Disposals of assets made before demolition.

Practical Tips

  • Review the risk report; Use your right to object.
  • Reserve contract clauses in contractor selection.
  • Check that the construction inspection company is independent.
  • Delivery time + penalty clause in the contract.
  • Rent assistance tracking.
  • Hiring a lawyer as a partner during the construction period.
  • Urban transformation files have multiple stakeholders. Real estate law lawyer recommended.

    Telif bildirimi This content and all related Q&A texts are protected under Turkish Copyright Law No. 5846. Unauthorized copying, reproduction, publication, adaptation, bulk extraction, or commercial use is prohibited; legal and criminal remedies are reserved in case of infringement.

    Hukuki destek arıyorsanız

    Bu konuda profesyonel hukuki destek için Aycan Ceylan Avukatlık Bürosu olarak yanınızdayız.

    Görüşme Planla